Veritas™ 5340 Appliance Hardware Installation Guide

Last Published:
Product(s): Appliances (Version Not Specified)
Platform: Veritas 5340
  1. Hardware overview
    1.  
      Supported software
    2.  
      5340 compute node and 5U84 storage shelves
    3.  
      5340 compute node and storage shelf power requirements
    4.  
      5340 compute node disk drives
    5.  
      5340 compute node control panel
    6.  
      5340 compute node rear panel
    7.  
      5U84 storage shelf drawers and disk drives
    8.  
      5U84 storage shelf control panel
    9.  
      5U84 storage shelf rear panel
    10.  
      5U84 storage shelf RAID controller
    11.  
      5U84 storage shelf Expansion module
    12.  
      Cables and connectors
  2. Preinstallation requirements
    1.  
      Customer-provided environment and supplies
    2.  
      Storage shelf shipping container contents
    3.  
      Compute node shipping container contents
    4.  
      Dimensions and determining rack locations
    5.  
      Best practices for rack installation
    6.  
      Heat dissipation guidelines
    7.  
      Cable length verification
    8.  
      Prerequisites for IPMI configuration
  3. Hardware installation procedures
    1.  
      Overview
    2.  
      Installing a storage shelf
    3.  
      Installing disk drives into a full-capacity storage shelf
    4.  
      Installing disk drives and blanks into a half-capacity storage shelf
    5.  
      Installing SFPs into the RAID controller
    6.  
      Installing the compute node rack rails
    7.  
      Installing the compute node into a rack
    8.  
      Connecting the hardware to one node
    9.  
      Connecting the hardware to two nodes
    10.  
      Connecting NetBackup nodes to the network
    11.  
      Connecting Flex nodes to the network
    12.  
      Connecting the power cords to the hardware
    13.  
      Turning on the hardware and verifying operation
    14.  
      Configuring the IPMI port from the NetBackup Appliance Shell Menu
    15.  
      Accessing and using the Veritas Remote Management interface
  4. Appendix A. Adding Expansion Storage Shelves to an operating appliance that does not have any Expansion shelves
    1.  
      Overview
    2.  
      Turning off the existing hardware
    3.  
      Installation instructions
    4.  
      Connecting one Expansion shelf to the Primary shelf
    5.  
      Connecting two Expansion shelves to the Primary shelf
    6.  
      Connecting three Expansion shelves to the Primary shelf
  5. Appendix B. Adding Expansion Storage Shelves to an operating appliance that has at least one operating Expansion shelf
    1.  
      Overview
    2.  
      Turning off the existing hardware
    3.  
      Installation instructions
    4.  
      Connecting one Expansion shelf to a system that has one existing Expansion shelf
    5.  
      Connecting two Expansion shelves to a system that has one existing Expansion shelf
    6.  
      Connecting one Expansion shelf to a system that has two existing Expansion shelves
  6. Appendix C. Configuring the disk space for new NetBackup Expansion Storage Shelves
    1.  
      Adding the disk space of an Expansion Storage Shelf from the NetBackup Appliance Web Console
    2.  
      Adding the disk space of an Expansion Storage Shelf from the NetBackup Appliance Shell Menu
  7. Appendix D. Configuring the disk space for new Flex Expansion Storage Shelves
    1.  
      Adding the disk space of an Expansion Storage Shelf from the Flex Appliance Console

Installing the compute node into a rack

After the storage shelves and the compute node rails have been installed, you can install the compute node into the rack. These instructions apply to a one-node system and to a multi-node system.

To install the compute node into the rack

  1. Verify that the rails are securely attached.
    • Verify that the outer rail is securely attached to the rack.

    • Pull the intermediate rail forward. Ensure that the ball bearing retainer is locked forward.

    • Verify that the inner rail is securely attached to the compute node.

  2. Place the hardware in the front of the rack.
  3. Slide the blue tab forward to unlock the intermediate rail.
  4. Pull the intermediate portion of rail the rail forward. Ensure that the ball bearing retainer on the intermediate rail is locked forward.

    Note:

    You do not need to extend the rails as far as they can possibly extend. You only need sufficient space to place the hardware into the rails.

  5. Align the compute node inner rail to the intermediate rail in the rack. Slide the compute node forward into the rack.

    The rail has a lock mechanism that prevents the hardware from being fully pushed into the rack.

  6. Slide the blue tab to unlock the rails and continue the sliding of the compute node into the rack.
  7. Secure the captive screws on the compute node ears.